Michigan OSHA citations issued the week of Aug 3, 2026
Week of Aug 3, 2026 · data as of October 5, 2026
66 inspections in Michigan had citations issued between Aug 3, 2026 and Aug 9, 2026, with 201 alleged violation items and $105,620 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
66inspections with citations issued
201alleged violation items
$105,620initial penalties
$75,070current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| C & L Ward Bros., Co. | Dewitt | Aug 7, 2026 | 3 | $6,500 | $3,500 | Informal settlementAbatement due Aug 26, 2026 | osha.gov | |
| J C Brick, Inc. | Northville | Aug 7, 2026 | 2 | $5,600 | $5,600 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| J&A Exterior LLC | Macomb | Aug 7, 2026 | 5 | $4,200 | $4,200 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Skye Construction LLC | Detroit | Aug 7, 2026 | 3 | $4,200 | $4,200 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Prestige Steel & Supply, Inc. | Lincoln Park | Aug 7, 2026 | 6 | $3,000 | $1,500 | Informal settlementAbatement due Aug 26, 2026 | osha.gov | |
| City of Marlette | Marlette | Aug 7, 2026 | 4 | $2,100 | $1,050 | Informal settlementAbatement due Aug 26, 2026 | osha.gov | |
| Lake Area Construction, LLC | East Jordan | Aug 7, 2026 | 7 | $2,000 | $2,000 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| George H. Pastor & Sons, Inc. | Mancelona | Aug 7, 2026 | 2 | $1,320 | $1,320 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| G.J. Perelli Co., LLC | Woodhaven | Aug 7, 2026 | 6 | $1,200 | $1,200 | Final order | osha.gov | |
| Tower Construction, LLC | Lincoln Park | Aug 7, 2026 | 1 | $800 | $800 | Final order | osha.gov | |
| JD Beard Construction, LLC | Howard City | Aug 7, 2026 | 6 | $400 | $400 | Final order | osha.gov | |
| Vanhook Builders LLC | Muskegon | Aug 7, 2026 | 5 | $400 | $400 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Albertos Construction Inc. | Northville | Aug 7, 2026 | 3 | $400 | $400 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Moore - Trosper Construction Co. | Mason | Aug 7, 2026 | 2 | $400 | $200 | OpenAbatement due Aug 26, 2026Contest deadline ~Aug 28, 2026 (est.) | osha.gov | |
| LA Maquina Construction LLC | Grand Rapids | Aug 7, 2026 | 4 | $400 | $400 | Final order | osha.gov | |
| Beatty Excavating LLC | Marlette | Aug 7, 2026 | 5 | $400 | $200 | OpenAbatement due Aug 26, 2026Contest deadline ~Aug 28, 2026 (est.) | osha.gov | |
| Commercial Contracting Corporation | Woodhaven | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| A-Better Exterior, LLC | Northville | Aug 7, 2026 | 1 | $0 | $0 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Lurvey Construction, LLC | Swartz Creek | Aug 7, 2026 | 1 | $0 | $0 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| J. W. Morgan Construction LLC | Swartz Creek | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Curt Moran Builders, Inc. | South Haven | Aug 7, 2026 | 2 | $0 | $0 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| TL Contracting, Inc. | Williamston | Aug 7, 2026 | 1 | $0 | $0 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Blaze Contracting, Inc. | Lincoln Park | Aug 7, 2026 | 3 | $0 | $0 | Final orderAbatement due Aug 26, 2026 | osha.gov | |
| Bloom Roofing Systems, Inc. | Southgate | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Countryside Heating & Cooling, Inc. | Portland | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| D & E Electric, LLC | Portland | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Top Notch Heating, Cooling & Geothermal, Inc. | Mancelona | Aug 7, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| I D Systems Inc. dba Inter Dyne Systems | Norton Shores | Aug 6, 2026 | 17 | $13,900 | $6,950 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Packaging Corporation of America | Filer City | Aug 6, 2026 | 2 | $5,000 | $5,000 | OpenContest deadline ~Aug 27, 2026 (est.) | osha.gov | |
| BCC Poured Walls & General Contracting, Inc. | Falmouth | Aug 6, 2026 | 5 | $3,600 | $1,800 | Informal settlementAbatement due Aug 25, 2026 | osha.gov | |
| Loadmaster Corporation | Norway | Aug 6, 2026 | 1 | $2,500 | $1,250 | Informal settlement | osha.gov | |
| City of Flint - City Hall | Flint | Aug 6, 2026 | 4 | $2,400 | $1,200 | OpenAbatement due Oct 9, 2026Contest deadline ~Aug 27, 2026 (est.) | osha.gov | |
| Lazaro Services LLC | Okemos | Aug 6, 2026 | 1 | $2,100 | $1,050 | Informal settlement | osha.gov | |
| McNeely Enterprises, Inc. | Brownstown Township | Aug 6, 2026 | 1 | $2,000 | $2,000 | ContestedAbatement due Aug 25, 2026Contested Jul 27, 2026 | osha.gov | |
| Murray Sprockets Inc. dba ABC Murray Sprockets Inc. | Warren | Aug 6, 2026 | 4 | $2,000 | $1,000 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Midwest Timer Service, Inc. | Benton Harbor | Aug 6, 2026 | 9 | $1,800 | $900 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Edge Material Management | Standish | Aug 6, 2026 | 4 | $1,500 | $750 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Equivalent Base Co. | Warren | Aug 6, 2026 | 8 | $1,200 | $600 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Menasha Packaging Company LLC | Coloma | Aug 6, 2026 | 1 | $1,000 | $1,000 | Final orderAbatement due Sep 16, 2026 | osha.gov | |
| Nitro-Vac Heat Treat Inc. | Warren | Aug 6, 2026 | 2 | $800 | $400 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| Alger County Transit Authority | Munising | Aug 6, 2026 | 3 | $300 | $150 | Informal settlementAbatement due Sep 9, 2026 | osha.gov | |
| LG Energy Solution Michigan Inc. | Lansing | Aug 6, 2026 | 2 | $0 | $0 | Final order | osha.gov | |
| Anglin Civil, LLC | Birmingham | Aug 6, 2026 | 1 | $0 | $0 | Final orderAbatement due Aug 25, 2026 | osha.gov | |
| Bay Masonry, LLC | Central Lake | Aug 6, 2026 | 1 | $0 | $0 | Final orderAbatement due Aug 25, 2026 | osha.gov | |
| JP Skidmore LLC | Menominee | Aug 6, 2026 | 6 | $0 | $0 | Final orderAbatement due Sep 9, 2026 | osha.gov | |
| Michigan Milk Producers Association | Constantine | Aug 5, 2026 | 3 | $4,200 | $2,100 | Informal settlementAbatement due Sep 15, 2026 | osha.gov | |
| Preferred Roofing Services, LLC | Cadillac | Aug 5, 2026 | 4 | $2,600 | $2,600 | Final orderAbatement due Aug 24, 2026 | osha.gov | |
| DT Manufacturing One LLC | Highland | Aug 5, 2026 | 2 | $2,000 | $1,000 | Informal settlementAbatement due Sep 8, 2026 | osha.gov | |
| Interkal LLC dba Interkal | Kalamazoo | Aug 5, 2026 | 1 | $900 | $450 | Informal settlementAbatement due Sep 15, 2026 | osha.gov | |
| Garber Chevrolet Saginaw | Saginaw | Aug 5, 2026 | 1 | $900 | $900 | Final orderAbatement due Sep 15, 2026 | osha.gov | |
| Hill Machine Works, LLC | Fraser | Aug 5, 2026 | 1 | $600 | $300 | Informal settlementAbatement due Sep 8, 2026 | osha.gov | |
| D.r. Trailer Sales, Inc. | Milan | Aug 5, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Collins Land Services LLC | Traverse City | Aug 5, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Edward Andrews International, Inc. | Sterling Heights | Aug 5, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Chalker Precision, LLC | Sterling Heights | Aug 5, 2026 | 1 | $0 | $0 | Final orderAbatement due Sep 8, 2026 | osha.gov | |
| The Salvation Army Echo Grove Camp and Retreat Center | Leonard | Aug 5, 2026 | 1 | $0 | $0 | Final orderAbatement due Sep 8, 2026 | osha.gov | |
| Name withheld (individual) | Westland | Aug 4, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Corrigan Oil Co. | Saginaw | Aug 3, 2026 | 3 | $7,000 | $7,000 | ContestedAbatement due Sep 18, 2026Contested Aug 24, 2026 | osha.gov | |
| Acorn Industries Inc. | Livonia | Aug 3, 2026 | 8 | $6,400 | $3,200 | Informal settlementAbatement due Sep 3, 2026 | osha.gov | |
| McPs Construction LLC dba Multi-County Property Services, LLC | Detroit | Aug 3, 2026 | 4 | $3,000 | $1,500 | Informal settlementAbatement due Sep 18, 2026 | osha.gov | |
| Master Electric, Inc. | Escanaba | Aug 3, 2026 | 3 | $2,000 | $2,000 | ContestedAbatement due Aug 20, 2026Contested Sep 14, 2026 | osha.gov | |
| Roy Ness Contracting & Sales, Inc. | Escanaba | Aug 3, 2026 | 4 | $1,700 | $1,700 | ContestedAbatement due Aug 20, 2026Contested Sep 8, 2026 | osha.gov | |
| Skye Construction LLC | Detroit | Aug 3, 2026 | 4 | $800 | $800 | Final orderAbatement due Sep 18, 2026 | osha.gov | |
| Cougar Contracting Inc. | Westland | Aug 3, 2026 | 2 | $100 | $100 | ContestedAbatement due Aug 20, 2026Contested Sep 12, 2026 | osha.gov | |
| Brad Couch Builders | Fruitport | Aug 3, 2026 | 1 | $0 | $0 | Final order | osha.gov | |
| Schmidt Bros Excavating, Inc. | Fruitport | Aug 3, 2026 | 4 | $0 | $0 | Final order | osha.gov |
Standards cited this week
- 1926.501 Fall Protection (9)
- 1910.1200 Hazard Communication (8)
- 1926.503 Fall Protection Training (4)
- 1910.134 Respiratory Protection (3)
- 1910.132 PPE General Requirements (3)
- 1926.1153 Silica in Construction (3)
- 1910.157 Fire Extinguishers (2)
- 1926.100 Hard Hats (2)
- 1910.147 Lockout/Tagout (2)
- 1910.22 Walking-Working Surfaces (2)
- 1910.1001 Asbestos (1)
- 1910.107 Spray Finishing (1)