Nevada construction: OSHA citations and most-cited standards

Data as of October 5, 2026

OSHA citations issued to construction establishments in Nevada over the last 12 months: volume by month, the standards cited most, penalties before and after settlement, and the most recently cited employers.

106inspections cited, last 12 months
17%of all cited inspections in Nevada
$4,020median initial penalty per inspection
$3,155median current penalty per inspection

Citations by month

Inspections with citations issued, by month of issuance. Hatched months are incomplete: citations reach the public data about a month after issuance.

Most-cited standards

StandardTopicInspectionsShare of construction inspections
1926.501Fall Protection2625%
NEVADA REVISED STATUTES 618.987(21211%
NEVADA REVISED STATUTES 618.987(11211%
1926.652Trench Cave-In Protection1110%
1926.503Fall Protection Training77%
1926.651Excavation Safety66%
LCB FILE NO. R069-20 (APPROVED AP55%
1926.1053Ladder Safety55%
1926.405Temporary Wiring and Cords44%
1926.150Construction Fire Protection44%
1910.134Respiratory Protection33%
LCB FILE NO. R131-24 (APPROVED NO33%

Sub-industries (NAICS)

Recently cited construction establishments

About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.

EstablishmentLocationIssuedStandards citedAlleged itemsInitial penaltyCurrent penaltyStatus and deadlinesSource
Veritas Managed Solutions, Inc. Sparks Sep 1, 2026 1926.405(b)(2)1 $0 $0 Final order osha.gov
Mammoth Underground LLC Las Vegas Aug 31, 2026 1926.652(b)1 $12,768 $12,768 OpenAbatement due Sep 8, 2026Contest deadline ~Sep 22, 2026 (est.) osha.gov
Gorman Roofing Services, LLC Las Vegas Aug 25, 2026 1926.501(b)(10), 1926.502(h)(1)2 $11,350 $11,350 OpenAbatement due Sep 2, 2026Contest deadline ~Sep 16, 2026 (est.) osha.gov
Southwest Industrial Electric Reno Aug 25, 2026 1926.1053(b)(1), 1926.652(a)(1)2 $7,094 $3,547 Informal settlement osha.gov
JP Flooring, LLC West Wendover Aug 25, 2026 1910.134(h)(2)(i), 1910.134(f)(1), 1910.134(e)(1), 1910.134(c)(1)4 $2,128 $2,128 Final order osha.gov
Rapid Alpine Construction Company LLC Reno Aug 12, 2026 1926.652(a)(1)1 $3,547 $1,774 Informal settlement osha.gov
Acco Engineered Systems Inc. Sparks Aug 10, 2026 1926.1412(d)(1), 1926.351(b)(4), 1926.405(a)(2)(ii)(I)3 $8,038 $8,038 Final order osha.gov
EC Company Sparks Aug 10, 2026 1926.452(w)(6)(i)1 $0 $0 ContestedContested Sep 15, 2026 osha.gov
H & E Construction, Inc. Reno Aug 7, 2026 1926.95(d)(1), 1926.454(a)2 $2,864 $2,864 ContestedAbatement due Aug 24, 2026Contested Sep 9, 2026 osha.gov
Rocky Mountain Grading LLC Las Vegas Jul 28, 2026 NEVADA REVISED STATUTES 618.987(11 $500 $250 Informal settlement osha.gov
Agate Construction, Inc. Reno Jul 24, 2026 NEVADA REVISED STATUTES 618.987(11 $500 $500 ContestedContested Aug 13, 2026 osha.gov
JT Thorpe Industrial, Inc. Sparks Jul 16, 2026 1926.451(f)(15)1 $7,035 $4,924 Informal settlement osha.gov
MPK Industrial Solutions, LLC Sparks Jul 16, 2026 NEVADA REVISED STATUTE 618.378(2)1 $3,150 $3,150 Final order osha.gov
Hartman-Walsh Painting Company Boulder City Jul 10, 2026 1910.303(b)(2), 1910.146(c)(4), 1904.40(a)3 $1,324 $1,324 Final orderAbatement due Jul 22, 2026 osha.gov
Facilities Management Inc. Reno Jul 6, 2026 1926.1101(k)(3)(ii), 1926.1101(g)(1), 1926.1101(e)(1), 1926.1101(h)(3)(iii)(A) +1 more5 $16,080 $8,040 Informal settlement osha.gov
Interior Specialists Inc. Las Vegas Jun 26, 2026 1926.50(g), 1926.102(a)(1)2 $12,058 $8,441 Informal settlementAbatement due Jul 6, 2026 osha.gov
Aztech Plastering, LLC Las Vegas Jun 26, 2026 LCB FILE NO. R069-20 (APPROVED AP, 1910.134(c)(2)(i)2 $8,308 $7,477 Informal settlementAbatement due Jul 6, 2026 osha.gov
Spectrum Construction LLC Las Vegas Jun 26, 2026 1926.416(e)(1)1 $0 $0 Final order osha.gov
Aztech Plastering, LLC Las Vegas Jun 26, 2026 1926.404(b)(1)(iii)(C)1 $0 $0 Final order osha.gov
LV-C.l.a.s.s., Inc. North Las Vegas Jun 25, 2026 NEVADA REVISED STATUTES 618.383(1, NEVADA REVISED STATUTES 618.378(22 $2,390 $2,390 Final order osha.gov
Silver State Framing System Pahrump Jun 23, 2026 1926.754(e)(2)(iii), 1926.760(a)(1), NEVADA REVISED STATUTE 618.378(1)3 $9,989 $9,989 OpenAbatement due Jun 26, 2026Contest deadline ~Jul 15, 2026 (est.) osha.gov
Platinum Plastering Inc. Las Vegas Jun 23, 2026 1910.1200(e)(1), LCB FILE NO. R069-20 (APPROVED AP2 $7,596 $7,596 ContestedAbatement due Jul 1, 2026Contested Jul 22, 2026 osha.gov
Platinum Plastering Inc. Las Vegas Jun 23, 2026 NEVADA REVISED STATUTES 618.987(2, 1926.34(c)2 $500 $500 ContestedAbatement due Jul 1, 2026Contested Jul 22, 2026 osha.gov
Silver State Building Systems LLC Las Vegas Jun 11, 2026 LCB FILE NO. R069-20 (APPROVED AP1 $5,534 $2,767 Informal settlement osha.gov
L C D Corp. Henderson Jun 11, 2026 1910.28(b)(1)(i)1 $3,547 $1,774 Informal settlementAbatement due Jun 16, 2026 osha.gov
Supreme Concrete, LLC Reno Jun 5, 2026 1910.22(c), 1910.28(b)(1)(i)2 $11,254 $5,627 Informal settlement osha.gov
Silver State Roofing LLC Fallon May 19, 2026 NEVADA REVISED STATUTES 618.987(1, NEVADA REVISED STATUTES 618.987(2, 1926.501(b)(13), 1926.503(a)(1)4 $8,094 $4,047 Informal settlement osha.gov
Ochoa Development Corporation Reno May 13, 2026 NEVADA ADMINISTRATIVE CODE 618.50, 1926.501(b)(4)(ii)2 $2,959 $1,480 Informal settlement osha.gov
Capriati Construction Corp., Inc. Reno May 13, 2026 NEVADA REVISED STATUTES 618.987(21 $500 $250 Informal settlementAbatement due May 26, 2026 osha.gov
Michael Sammler Roofing Inc. Reno May 7, 2026 NEVADA REVISED STATUTES 618.987(2, NEVADA REVISED STATUTES 618.987(1, 1926.503(b)(1), 1926.501(b)(13)4 $4,547 $2,274 Informal settlementAbatement due May 18, 2026 osha.gov
Hill & Hill Construction LLC Boulder City May 6, 2026 1910.178(l)(1)(i)1 $8,441 $1,328 Informal settlement osha.gov
M.J. Constructions Co. Las Vegas May 1, 2026 1926.34(c)1 $2,837 $2,837 Final order osha.gov
Reliable Framing, Inc. Reno May 1, 2026 1926.404(f)(6)1 $0 $0 Final order osha.gov
Rhyno Built LLC Minden Apr 30, 2026 1926.501(b)(1)1 $4,020 $4,020 Final order osha.gov
United Construction Company Reno Apr 28, 2026 1926.501(b)(4)(ii)1 $1,628 $814 Informal settlement osha.gov
New Life Steel LLC Reno Apr 23, 2026 1926.760(a)(1), NEVADA REVISED STATUTES 618.987(22 $4,520 $2,260 Informal settlementAbatement due May 28, 2026 osha.gov
Storage Building Company, LLC Reno Apr 22, 2026 1926.760(a)(1)1 $4,020 $4,020 Final order osha.gov
KP Construction, Inc. Reno Apr 21, 2026 NEVADA REVISED STATUTES 618.987(21 $500 $500 Final orderAbatement due May 26, 2026 osha.gov
Braemar Construction LLC Winnemucca Apr 20, 2026 1926.100(a), 1926.150(c)(1)(i), 1926.501(b)(13), 1926.503(a)(1) +3 more7 $31,451 $15,726 Informal settlementAbatement due Apr 28, 2026 osha.gov
Lancaster Burns Construction, Inc. Incline Village Apr 20, 2026 1926.403(b)(1)(ii)1 $5,627 $5,627 ContestedContested Apr 29, 2026 osha.gov
Stonehouse Drilling & Construction, LLC Winnemucca Apr 20, 2026 1910.212(a)(1)1 $3,215 $3,215 Final orderAbatement due Apr 28, 2026 osha.gov
Arco DB Companies, Inc. Sparks Apr 16, 2026 1926.501(b)(4)(ii)1 $8,867 $8,867 ContestedContested May 15, 2026 osha.gov
FDR Construction, Inc. Sparks Apr 16, 2026 1926.501(b)(1)1 $3,547 $1,774 Informal settlement osha.gov
AMS Fire Protection LLC Sparks Apr 16, 2026 NEVADA REVISED STATUTES 618.987(11 $500 $500 Final order osha.gov
Mountain West Builders, LLC Spanish Springs Apr 13, 2026 1926.150(c)(1)(viii)1 $3,310 $3,310 Final order osha.gov
NRD Nevada Roofing Division LLC Reno Apr 8, 2026 1926.501(b)(10), NEVADA REVISED STATUTES 618.987(12 $3,160 $3,160 Final orderAbatement due May 18, 2026 osha.gov
Pro Glass and Mirror Inc. Incline Village Apr 7, 2026 NEVADA REVISED STATUTES 618.987(2, NEVADA REVISED STATUTES 618.378(2, NEVADA REVISED STATUTES 618.987(13 $1,339 $1,339 Final orderAbatement due Apr 27, 2026 osha.gov
Boc-Nevada, Inc. Incline Village Mar 23, 2026 NEVADA REVISED STATUTES 618.987(2, 1926.502(b)(3)2 $4,047 $4,047 ContestedAbatement due Apr 16, 2026Contested May 20, 2026 osha.gov
Sbi Roofing Reno Mar 20, 2026 1926.501(b)(10)1 $3,547 $3,547 Final order osha.gov
Urata & Sons Concrete, LLC Incline Village Mar 20, 2026 1926.1053(b)(16)1 $3,215 $2,250 Informal settlement osha.gov
The 50 most recent of 106 cited inspections.

Other industries in Nevada

Questions

How many construction employers in Nevada were cited by OSHA?

106 construction inspections in Nevada had citations issued in the 12 months to Oct 5, 2026, 17% of all cited inspections in the state.

What do OSHA inspectors cite most in Nevada construction?

The most-cited standards were 1926.501 (Fall Protection), NEVADA REVISED STATUTES 618.987(2, NEVADA REVISED STATUTES 618.987(1.

What is the typical penalty for construction employers in Nevada?

Median initial penalty per cited inspection: $4,020. Median current penalty: $3,155.