Iowa OSHA citations issued the week of Mar 16, 2026
Week of Mar 16, 2026 · data as of October 5, 2026
16 inspections in Iowa had citations issued between Mar 16, 2026 and Mar 22, 2026, with 40 alleged violation items and $266,201 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
16inspections with citations issued
40alleged violation items
$266,201initial penalties
$160,578current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Acme Test Products Company | Clarence | Mar 21, 2026 | 1 | $500 | $500 | OpenAbatement due Mar 26, 2026Contest deadline ~Apr 10, 2026 (est.) | osha.gov | |
| Dee Zee, Inc. | Pleasant Hill | Mar 19, 2026 | 2 | $59,107 | $26,007 | Informal settlementAbatement due May 5, 2026 | osha.gov | |
| Agriland FS, Inc. | Underwood | Mar 19, 2026 | 3 | $44,685 | $35,748 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Wildhawk Investments, LLC | Washington | Mar 19, 2026 | 2 | $18,914 | $9,457 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Smurfit Westrock Cedar Rapids Iowa | Cedar Rapids | Mar 19, 2026 | 1 | $12,768 | $7,000 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Engineered Plastic Components | Kalona | Mar 19, 2026 | 1 | $10,640 | $5,320 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Name withheld (individual) | Red Oak | Mar 19, 2026 | 1 | $6,384 | $3,192 | Informal settlement | osha.gov | |
| Manly Terminal LLC | Manly | Mar 19, 2026 | 3 | $4,256 | $2,128 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Triple K Manufacturing Co. | Shenandoah | Mar 19, 2026 | 1 | $2,128 | $1,064 | Informal settlementAbatement due Apr 14, 2026 | osha.gov | |
| Modtek Engineering | Des Moines | Mar 19, 2026 | 1 | $1,891 | $1,891 | Final order | osha.gov | |
| C&H Construction LLC | Spirit Lake | Mar 18, 2026 | 11 | $19,860 | $9,930 | Informal settlementAbatement due Apr 13, 2026 | osha.gov | |
| Coronado Construction LLC | Spirit Lake | Mar 18, 2026 | 1 | $9,930 | $3,310 | Informal settlementAbatement due Apr 13, 2026 | osha.gov | |
| John Deere Dubuque Works | Dubuque | Mar 16, 2026 | 2 | $29,790 | $25,321 | Informal settlementAbatement due Apr 30, 2026 | osha.gov | |
| Zulu Construction | Cedar Rapids | Mar 16, 2026 | 3 | $22,698 | $13,618 | Informal settlementAbatement due Apr 2, 2026 | osha.gov | |
| Cargill Inc. | Eddyville | Mar 16, 2026 | 2 | $15,558 | $9,000 | Informal settlementAbatement due Apr 9, 2026 | osha.gov | |
| Protein Resources, Inc. | West Bend | Mar 16, 2026 | 5 | $7,092 | $7,092 | Final orderAbatement due Apr 30, 2026 | osha.gov |
Standards cited this week
- 1910.147 Lockout/Tagout (3)
- 1910.132 PPE General Requirements (2)
- 1910.178 Forklifts (2)
- 1926.20 Construction Safety Programs (2)
- 1910.28 Fall Protection Duty (2)
- 1910.212 Machine Guarding (2)
- 1910.184 Rigging Slings (1)
- 1910.1200 Hazard Communication (1)
- 1904.29 OSHA 300 and 301 Forms (1)
- 1910.22 Walking-Working Surfaces (1)
- 1910.23 Ladders (1)
- 1910.272 Grain Handling (1)