13 inspections in Maryland had citations issued between Jun 15, 2026 and Jun 21, 2026, with 72 alleged violation items and $49,887 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
13inspections with citations issued
72alleged violation items
$49,887initial penalties
$49,307current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Rmo Carpentry LLC | Brunswick | Jun 17, 2026 | 3 | $15,000 | $15,000 | Final orderAbatement due Jun 25, 2026 | osha.gov | |
| JBS Framing Construction LLC | Baltimore | Jun 17, 2026 | 6 | $9,500 | $9,500 | Final orderAbatement due Jun 25, 2026 | osha.gov | |
| B&S Construction LLC | Ocean City | Jun 17, 2026 | 10 | $3,587 | $3,587 | Final orderAbatement due Jun 25, 2026 | osha.gov | |
| CBD of Maryland Painting Inc. | Cockeysville | Jun 17, 2026 | 3 | $0 | $0 | Final orderAbatement due Jun 25, 2026 | osha.gov | |
| Fischer Roofing, LLC | Dundalk | Jun 15, 2026 | 4 | $4,950 | $4,950 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| A&A Smart Contractor LLC | Dundalk | Jun 15, 2026 | 7 | $4,700 | $4,700 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| Daav General Construction LLC | Ocean Pines | Jun 15, 2026 | 7 | $3,400 | $3,400 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| Jr Framing Carpentry LLC | Nottingham | Jun 15, 2026 | 9 | $3,000 | $3,000 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| Keep IT Clean Landscape & Trash Removal | Baltimore | Jun 15, 2026 | 6 | $2,100 | $2,100 | OpenAbatement due Jun 23, 2026Contest deadline ~Jul 8, 2026 (est.) | osha.gov | |
| Name withheld (individual) | Perry Hall | Jun 15, 2026 | 2 | $1,400 | $1,400 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| Cleary's Transportation Co., Inc. | Street | Jun 15, 2026 | 8 | $1,200 | $1,200 | Final orderAbatement due Jun 23, 2026 | osha.gov | |
| BCM Solutions LLC | Dundalk | Jun 15, 2026 | 5 | $1,050 | $470 | Formal settlementAbatement due Jun 23, 2026Contested Jun 26, 2026 | osha.gov | |
| Harvey Construction Inc. | Cockeysville | Jun 15, 2026 | 2 | $0 | $0 | Final order | osha.gov |
Standards cited this week
- 1926.501 Fall Protection (9)
- 1926.503 Fall Protection Training (6)
- 1926.102 Eye and Face Protection (5)
- 1926.1053 Ladder Safety (5)
- 1926.20 Construction Safety Programs (4)
- 1926.100 Hard Hats (4)
- 1910.1200 Hazard Communication (4)
- 1926.1060 Ladder and Stair Training (2)
- 1926.452 Specific Scaffold Types (2)
- 1904.32 OSHA 300A Annual Summary (1)
- 1904.39 Severe Injury Reporting (1)
- 1904.4 Injury Recording Criteria (1)