Great Northern Innovation, LLC: OSHA inspection records
Data as of October 5, 2026
- Location
- 305 Tiger Street, Milltown, WI 54858
- Industry
- Manufacturing (NAICS 326299)
- Jurisdiction
- Wisconsin, Federal OSHA
- Cited inspections
- 2 in the last 12 months
- Inspection history
- Inspected 3 times since 2025; 3 of those inspections had citations. OSHA records at the same establishment name and ZIP code.
Alleged violations. The items below are citations issued by federal OSHA. They are allegations and proposed penalties, not findings of wrongdoing, unless and until they become final orders. Employers may contest citations or settle them, and items may be reduced, reclassified or withdrawn. The status label and the original and current penalties are taken from the public record as of October 5, 2026.
Inspection 348791435
Informal settlement Resolved through an informal settlement agreement.
- Opened
- March 4, 2026
- Citations issued
- June 26, 2026
- Abatement due
- July 20, 2026 (per OSHA record)
- Final order date
- July 6, 2026 (per OSHA record)
- Official record
- osha.gov inspection detail 348791435
| Citation | Standard | Type | Issued | Abatement due | Initial penalty | Current penalty | Status |
|---|---|---|---|---|---|---|---|
| Citation 01001 | 1910.212(a)(3)(ii) Machine Guarding | Serious | Jun 26, 2026 | Jul 20, 2026 | $7,035 | $4,924 | Informal settlement |
| Citation 01002A | 1910.219(d)(1) Power Transmission Guarding | Serious | Jun 26, 2026 | Jul 20, 2026 | $7,035 | $4,924 | Informal settlement |
| Citation 01002B | 1910.219(e)(3)(i) Power Transmission Guarding | Serious | Jun 26, 2026 | Jul 20, 2026 | $0 | $0 | Informal settlement |
Inspection 348792144
Informal settlement Resolved through an informal settlement agreement.
- Opened
- March 4, 2026
- Citations issued
- June 18, 2026
- Abatement due
- August 10, 2026 (per OSHA record)
- Final order date
- June 30, 2026 (per OSHA record)
- Official record
- osha.gov inspection detail 348792144
| Citation | Standard | Type | Issued | Abatement due | Initial penalty | Current penalty | Status |
|---|---|---|---|---|---|---|---|
| Citation 01001A | 1910.134(c)(1) Respiratory Protection | Serious | Jun 18, 2026 | Aug 10, 2026 | $4,220 | $2,954 | Informal settlement |
| Citation 01001B | 1910.134(e)(1) Respiratory Protection | Serious | Jun 18, 2026 | Aug 10, 2026 | $0 | $0 | Informal settlement |
| Citation 01001C | 1910.134(d)(1)(iii) Respiratory Protection | Serious | Jun 18, 2026 | Aug 10, 2026 | $0 | $0 | Informal settlement |
| Citation 01001D | 1910.134(k)(1) Respiratory Protection | Serious | Jun 18, 2026 | Aug 10, 2026 | $0 | $0 | Informal settlement |
| Citation 01002 | 1910.303(b)(2) Electrical General | Serious | Jun 18, 2026 | Aug 10, 2026 | $4,220 | $2,954 | Informal settlement |
| Citation 02001 | 1904.32(a)(4) OSHA 300A Annual Summary | Other-than-serious | Jun 18, 2026 | Aug 10, 2026 | $0 | $0 | Informal settlement |
| Citation 02002 | 1910.37(b)(2) Exit Route Maintenance | Other-than-serious | Jun 18, 2026 | Aug 10, 2026 | $0 | $0 | Informal settlement |
Earlier inspections at this establishment
Other OSHA inspections recorded at the same establishment name and ZIP code, newest first. Penalties are the initial (proposed) amounts; open the official record for the outcome.
| Inspection | Opened | Alleged items | Initial penalty | Source |
|---|---|---|---|---|
| Inspection 348262288 | May 20, 2025 | 3 | $16,882 | osha.gov |
Related
- Wisconsin OSHA citations
- Wisconsin manufacturing citations
- 1910.212 Machine Guarding
- 1910.303 Electrical General
- 1910.134 Respiratory Protection
- 1910.37 Exit Route Maintenance
- 1910.219 Power Transmission Guarding
- 1904.32 OSHA 300A Annual Summary