New York OSHA citations issued the week of Jul 20, 2026
Week of Jul 20, 2026 · data as of October 5, 2026
13 inspections in New York had citations issued between Jul 20, 2026 and Jul 26, 2026, with 34 alleged violation items and $92,251 in proposed penalties. Statuses and current penalties reflect the data as of October 5, 2026.
13inspections with citations issued
34alleged violation items
$92,251initial penalties
$50,470current penalties
About these records. Citations list alleged violations and proposed penalties. Employers can contest them, and many are reduced or withdrawn in settlement. Each row shows the original and the current penalty and a status label derived from the public data as of October 5, 2026. Check the linked osha.gov page for the official record.
| Establishment | Location | Issued | Standards cited | Alleged items | Initial penalty | Current penalty | Status and deadlines | Source |
|---|---|---|---|---|---|---|---|---|
| Empire Timber Framing, LLC | Syracuse | Jul 24, 2026 | 2 | $4,597 | $398 | Formal settlementAbatement due Jun 2, 2026Contested Aug 11, 2025 | osha.gov | |
| Nysdoccs Upstate Correctional Facility | Malone | Jul 24, 2026 | 2 | $0 | $0 | Final orderAbatement due Sep 10, 2026 | osha.gov | |
| Welded Tube USA, Inc. | Lackawanna | Jul 23, 2026 | 6 | $32,923 | $15,000 | OpenAbatement due Aug 18, 2026Contest deadline ~Aug 13, 2026 (est.) | osha.gov | |
| Westchester Roofing Group Inc. | Peekskill | Jul 23, 2026 | 2 | $20,428 | $12,500 | Informal settlement | osha.gov | |
| Cannonsville Lumber, Inc. | Deposit | Jul 23, 2026 | 2 | $4,085 | $1,844 | Informal settlementAbatement due Dec 23, 2024 | osha.gov | |
| Watkins Glen Village Water Treatment Plant | Watkins Glen | Jul 23, 2026 | 3 | $0 | $0 | Final orderAbatement due Aug 11, 2026 | osha.gov | |
| Utica City Fire Department Fire Academy | Utica | Jul 23, 2026 | 1 | $0 | $0 | Final orderAbatement due Sep 9, 2026 | osha.gov | |
| Utica City Fire Department Fire Academy | Utica | Jul 23, 2026 | 5 | $0 | $0 | Final orderAbatement due Aug 11, 2026 | osha.gov | |
| Mid Hudson Building Contractors, Inc. | Pleasantville | Jul 22, 2026 | 3 | $10,214 | $7,250 | Informal settlement | osha.gov | |
| Hudson Valley Solar Solutions Inc. | Ardsley | Jul 22, 2026 | 1 | $7,944 | $3,972 | Informal settlement | osha.gov | |
| Miller Mechanical Services, Inc. | Glens Falls | Jul 21, 2026 | 1 | $8,513 | $5,959 | Informal settlementAbatement due Jul 27, 2026 | osha.gov | |
| FBT Construction, Inc. | East Hampton | Jul 20, 2026 | 1 | $3,547 | $3,547 | Final order | osha.gov | |
| Cohoes City DPW | Cohoes | Jul 20, 2026 | 5 | $0 | $0 | Final orderAbatement due Aug 6, 2026 | osha.gov |
Standards cited this week
- 1926.501 Fall Protection (3)
- 1926.102 Eye and Face Protection (2)
- 1903.19 Abatement Verification (2)
- 1904.39 Severe Injury Reporting (1)
- 1910.132 PPE General Requirements (1)
- 1910.135 Head Protection (1)
- 1910.133 Eye & Face Protection (1)
- 1910.141 Sanitation (1)
- 1910.146 Confined Spaces (1)
- 1910.212 Machine Guarding (1)
- 1910.28 Fall Protection Duty (1)
- 1910.147 Lockout/Tagout (1)